Free YouTube Transcribe

Video transcript

Japan's $20 Billion Airport Is Slowly Sinking Into the Ocean

GyaanProcess · 1,568 words · 8 min read

Want to search this transcript, jump the video from any line, or download it as TXT, SRT, or VTT?

Open in the transcript tool

Full transcript

0:00An airport built in the middle of the

0:03sea that is still slowly sinking today .

0:06This is Kansai International Airport in

0:08Japan's Osaka Bay . It was not a natural

0:11island . It was created by humans from

0:14the sea . It cost approximately 20

0:17billion . Construction began in 1987 ,

0:20and the first phase opened on September

0:234 , 1994 . But the real story of this

0:26airport is not about the terminal or

0:28runways . The true story is hidden

0:31underground where the human eye cannot

0:33see . There was an enemy there that was

0:36very difficult to defeat . The soft sea

0:39soil that could pull everything down .

0:42If the engineers hadn't used the right

0:45method , the entire island could have

0:47collapsed . In this video , we will see

0:50how Japan turned the sea into land . An

0:53engineering story that still amazes the

0:56world today . Let's start with this

0:59unique story from beneath the sea .

1:02Engineers chose a spot in the sea 5 km

1:05away from Osaka . The water depth there

1:08was about 18 meters . The first island

1:11was to be built , spreading over 510

1:13hectares . But when engineers examined

1:16the seabed , they found a major

1:17difficulty . Beneath the sea was a thick

1:21layer of soft soil called marine clay .

1:24This soil was so soft that normal

1:27construction was not possible . If soil

1:30were dumped directly , its weight would

1:32compress the clay . Compressing it would

1:35push the water out of the clay , causing

1:37the whole island to sink . Meaning ,

1:40starting construction directly meant

1:42the entire airport would sink .

1:44Therefore , it was necessary to prepare

1:46the ground first . Before building any

1:48structures . This challenge was one of

1:51the world's most difficult marine

1:53engineering projects . Now let's see how

1:56engineers made this soft soil strong .

1:59This is a story of controlling the land

2:02from beneath the sea . First , a 1.5 -

2:05meter-thick sand blanket was laid on

2:07the seabed . This sand blanket acted as

2:11a foundational layer . Then engineers

2:14installed nearly 1 million vertical

2:16sand drains . These drains were placed

2:19in a 2.5 - meter grid . The job of these

2:22thousands of drains was to provide a

2:24path for water from within the clay . As

2:26the water was removed , the soil

2:28gradually became stronger . But sand

2:31drains alone were not enough . Engineers

2:34also used sand compaction piles , and a

2:37deep cement mixing technique was

2:39adopted . The goal of all this was to

2:42make the ground strong enough to

2:44support the seawall and the entire

2:46island's weight . After months of hard

2:50work , the seafloor was now ready for

2:52construction . Now it was time to build

2:55a wall around this land . This was the

2:58next big step in this impossible

3:01project . The ground had become stable .

3:03Now it was time to build a massive

3:06seawall around it . Construction of the

3:09seawall began in January 1987 . The

3:12design was a robust rubble-mound

3:14structure . A solid framework of stones

3:17and boulders . First , large stones were

3:20lowered onto the seabed from barges as

3:23a foundation . The size and placement of

3:27each stone were carefully planned to

3:29distribute weight . Above the foundation

3:32, stones ranging from large to small

3:34were laid layer by layer . Each layer's

3:38job was to break the force of the waves

3:40to protect the interior . On top ,

3:44special concrete armor blocks like

3:47tetrapods or interlocking blocks were

3:50used . These blocks kept the seawall in

3:55place even during stormy waves . Work

3:58continued day and night . New barges

4:00arrived every day with fresh material .

4:03Engineers constantly checked the height

4:06and alignment to ensure no deviation .

4:09In some sections , the seawall was built

4:12much higher than the sea level . For

4:14protection against storm surges and

4:17waves . Finally , in June 1989 , the 11 km

4:21long seawall was fully completed . Now ,

4:25the sea inside had become an enclosed

4:27area . The next task was to turn it into

4:30dry land . The seawall was the very

4:33foundation of the entire project . The

4:36seawall was completely ready . Now , the

4:38empty sea inside had to be turned into

4:41land . Large vessels carrying soil and

4:43sand arrived inside the seawall

4:45continuously . About 180 million cubic

4:47meters of reclamation material was

4:49needed for the first island . This

4:51material was cut from various mountains

4:53in Japan . Through special mountain

4:55cutting projects . Each ship would drop

4:58its load . Then bulldozers would spread

5:01it out evenly . Material was added layer

5:04by layer , and each layer was thoroughly

5:06compacted . Compaction was crucial to

5:10ensure the new ground was strong from

5:12the start . Slowly , the seabed began to

5:16disappear , and a new piece of land

5:18emerged . Within a few months , solid

5:21ground could be seen where there was

5:23only water . But the soft clay

5:25underneath began to sink under the new

5:28weight . This meant the new island was

5:32still gradually settling . This

5:34settlement was no accident . Engineers

5:37had included it in the design from the

5:39very beginning . The first phase of

5:42reclamation was largely finished by

5:451990 . Now the next challenge was to

5:48control this sinking land for years .

5:51Engineers began to constantly measure

5:54the island's settlement . By installing

5:56special sensors . Hydraulic jacks were

5:59installed under every structure to

6:01adjust the elevation as the ground

6:03settled . Whenever the ground sank by a

6:05few millimeters , the jacks would

6:07straighten the structure back up . This

6:10jacking system was installed under

6:12almost every major pillar of the

6:13airport . To manage this challenge , the

6:17sea walls were also raised from time to

6:18time . Brand new underground systems

6:22were also built to control groundwater

6:24and seawater . A major step was building

6:28underground water barriers that go down

6:30to 30 meters . These barriers prevent

6:33seawater from seeping inside .

6:35Especially during storm surges . By

6:38December 2025 , the island's average

6:41settlement had reached 13.72 meters . Of

6:45this , approximately 9.82 meters . Had

6:48already occurred before the airport

6:50even opened . The rest of the settlement

6:52happened over the years . But now , its

6:54pace has slowed down significantly .

6:57This is how humans kept a sinking

6:59landmass under control for years . But

7:02only the ground was ready for now . The

7:05entire airport above it was yet to be

7:07built . Both the foundation and the

7:09design were ready . Now it was time to

7:11construct the actual building . First , a

7:143,500 - meter-long runway was built on

7:16the island . Simultaneously , the

7:18taxiways also began to take shape . The

7:21terminal was designed by Renzo Piano

7:23Building Workshop , and Nikken Sekkei

7:25handled the structural design .

7:27Construction was managed by the

7:29Takenaka joint venture . The terminal's

7:31area was 291,270 . Square meters . The

7:37terminal's long curved shape was

7:38specifically chosen to facilitate

7:40passenger movement . First , steel

7:43columns were erected . Then , large steel

7:45trusses were placed on top of them . A

7:48special curved roof design , built for

7:50natural airflow , was fitted onto these

7:52trusses . After the roof was installed ,

7:55the entire building was covered with

7:56glass facets . Inside , baggage handling ,

7:59security , gates , and mechanical systems

8:01were installed . A large bridge was also

8:05built to connect the island to the

8:07mainland . The bridge had two levels .

8:09One for road traffic and the other for

8:12trains . The bridge was completed in

8:15March 1994 . In June , the terminal was

8:19also fully ready , and finally , on

8:21September 4 , 1994 , Kansai International

8:24Airport officially opened . But the

8:27story did not end there . Japan soon

8:29needed another runway . This time , the

8:32decision was made to build a second

8:35island in even deeper water . The second

8:38island spanned 545 hectares . Even

8:40further offshore than the first . The

8:43entire process was repeated again .

8:45Seabed prep , sea wall , reclamation ,

8:47monitoring . This time the water was

8:50deeper , and the clay layer was thicker

8:52than before . Therefore , the number of

8:55sand drains and compaction piles was

8:57also increased . For construction this

9:00time , 250 million cubic meters of

9:02material was used . The seawall was also

9:05designed to be longer and stronger this

9:07time . After years of hard work , a new

9:104,000 - meter runway was completed . This

9:13runway entered service in 2007 , and the

9:16airport's capacity doubled . Even today ,

9:19engineers continuously monitor this

9:22sinking land . First the land was made ,

9:24then the seawall was built , then

9:26settlement was controlled . Only then

9:28was the airport established . That is

9:30why Kansai is not just an airport , but

9:32one of the greatest marine engineering

9:34stories in the world . If you liked this

9:38story , please like the video and be

9:39sure to subscribe to the channel .

Recently added transcripts

Browse the whole transcript library

This transcript was generated from the captions YouTube publishes for this video. Get the transcript of any YouTube video atfreeyoutubetranscribe.com, free, unlimited, no sign-up.